Ir-192 Exposure Time Calculator for Fix Thickness Steel Job (CS)

Ir-192 Exposure Time Calculator for Fix Thickness Steel Job (CS)

Ir-192 Exposure Time Calculator for Fix Thickness Steel Job

Ir-192 Exposure Time Calculator for Fix Thickness Steel Job (CS)

(toc)

Ir-192 Exposure Time Calculator for Fix Thickness Steel Job

Select Thickness, Source to Film Distance (SFD) and Source Activity then Formula give you Exposure Time in minutes Use them

Ir-192 Exposure Time Calculation Tool

Ir-192 Exposure Time Calculator for Fix Thickness Steel Job










Ir-192 Exposure Time Calculator Table and use for Fix Thickness Steel Job

Table- for Thickness and that mortification factor value use of this Table give below Formula and found Exposure Time easily for Normal Industrial Film like D-7 film exposure time calculation in this Post
Thickness in (mm)Factor Value
40.025
60.028
80.031
100.034
120.038
140.041
160.045
180.05
200.054
220.06
250.068
280.081
300.088
320.099
350.11
380.13
400.14
450.16
500.232
550.304
600.376
650.496
700.64
750.776
801.04
851.34
901.7
952.2
1002.64
1053.5
1104.5
1156
1207.4
Use of above table 
Exposure Time = FV x SFD x SFD / (Ci)

here is:    FV =        Mortification Factor Value according to job Thickness
                SFD =    Source to Film Distance in cm
                Ci = Source Current Activity in Ci

X-Ray Machine Exposure Time Table for Steel Job

here Fix Exposure time Table of Steel job according to Job Thickness and SFD given belows
Thickness in (mm)KV (Voltage)SFD (cm)Exposure time (Current)
5160455 Points (30 seconds)
10170451.0 Minutes
16200601.7 Minutes
20200602.7 Minutes
25200603.0 Minutes
30230544 Minutes
32230546 Minutes
36240508 Minutes